The refurbishment of the Chemistry Building is being carried out in stages – different parts of the building are renovated in different phases to minimize the impact on operations. During fall 2026, work starts in Fysik Trapphuset. Meanwhile, several parts of the Chemisty Building are being finished.
The following major works are taking place in the Chemistry Building and Fysik Trapphuset during fall 2026:
Research Building 1
Work is ongoing on floor 1 creating a new entrance facing the Vasa area, including a new elevator.
Work is ongoing on floor 7, creating new student areas towards Övergången.
Local work is being carried out within the divisions.
Course Building
Work is ongoing on floor 4 with new teaching laboratories and learning environments for basic education.
Work is ongoing on floor 5 with new teching laboratories for basic education.
Local work is being carried out within the divisions.
Research Building 2
Work is ongoing on floor 1, where student facilities as well as group rooms and study areas for the basic education are being created.
Local work is being carried out within the divisions.
Fysik Trapphuset
Work is ongoing on floor 1 with new group rooms and study areas for the basic education.
Work is ongoing on floor 2 and 3 with new office and lab facilities.